Selected Civil Infrastructure Projects

EvoEnergy Underground Electricity Service Upgrades

BMCA has been providing project management and surveillance services to EvoEnergy on the civil construction upgrades of underground electricity services.

After a number of issues with damage to underground services from civil contractors undertaking Horizontal Directional Drilling (HDD) work on behalf of EvoEnergy, BMCA’s specialist civil construction expertise was employed to reduce the risk of damage to adjacent facilities and services.

From 2017 to 2019, BMCA completed four projects for power supply to substations in Gungahlin and Barton, and is currently undertaking a fifth for the Edinburgh Feeder in Acton scheduled for completion in 3Q2019.

Gundaroo Drive Duplication 2018-2019

BMCA is leading a joint team to provide PAP and surveillance services to the ACT Government for Stage 2 of the duplication of Gundaroo Drive from Crace to Gungahlin.

Works commenced early second quarter 2018. The construction scope includes earthworks, stormwater, services relocation, three bridges, flexible pavements, road furniture, street lighting and landscaping, with completion scheduled for late 2019

 

 

Horse Park Drive Duplication 2017 – 2019

BMCA teamed with AECOM to provide superintendency and surveillance services to the ACT Government for Multiple Segments of the duplication of Horse Park Drive in Gungahlin.

Works were completed on all segments mid 2019. The $25m project scope included earthworks, stormwater, services relocations, two bridges, flexible pavements, road furniture, street lighting and landscaping.

 

Cotter Road Stage 2 Duplication 2017-2018

A recently completed $20 million project for duplication of the existing road between Tuggeranong Parkway and McCulloch Street. Works included construction and reconstruction of new and existing bridges over Yarralumla Creek, as well as cyclist & pedestrian paths and associated landscaping.

North Weston Odour Control Project 2018

Contract administration on behalf of Icon Water for a new fanhouse, foul air offtake and fresh air inducts for the Molonglo Valley Interceptor Sewer. Construction was completed late 2018, with scope including reinforced concrete building construction, mechanical and electrical equipment procurement and installation and commissioning.North Weston Odour Control Project 2018

 

ACT Healthy Waterways 2017

A federally funded project to undertake water quality improvements at multiple sites over 6 catchment areas in the ACT and neighbouring NSW.

BMCA provided construction planning advice, including for procurement of contracting services, establishment of contract administration processes and other inputs to detailed designs.

Googong Township Water Supply 2016 – 2017

BMCA undertook superintendency and surveillance of two projects on behalf of Client GTPL for the supply of water to the new and expanding Googong Township, with works substantially completed late 2017. The works undertaken are for upgrades to the existing pumping station, pipeline and metering facilities at Googong Dam (IWC East) and water storage reservoirs, treatment systems, gravity and pumping mains for potable and recycled water (IWC West). The total value of works is approximately $15 million, executed by local contractor Guideline ACT

 

 

Googong Water Treatment Plant  2015

Client – Googong Town Council Services – Contracts Administration, Site Surveillance Project Cost > AUD 20 million A stand-alone waste water treatment facility providing non-potable recycled water to the surrounding community through a dedicated reticulation network. Initial design for service of 3,600 people. The project is a key element of the larger Integrated Water Cycle Network for Googong, which will service 18,850 people.

Edwin Land Parkway 2012

Contract administration and Surveillance on a 2.3km long arterial road involving 60,000m3 of earthworks resulting from a significant cutting, services relocations, storm water infrastructure, cycleways, a signalized intersection, landscaping and lighting Key activities included, contract administration, Client reporting, project controls (cost and program), and coordination with Design and Construction contractors

Cotter/Kirkpatrick Intersection  2013

Client – Procurement & capital Works – Contracts Administration, Site Surveillance Project Cost – > AUD 20 million The project commenced in November 2011 and involved removal of an existing roundabout, construction of a new signalised intersection, and reconstruction of approximately 600m of dual carriageway on Cotter Road. Significant challenges on the project included relocated telecommunications infrastructure, simultaneous operations with heavy traffic on Cotter Road and Relocation and consolidation of major telecommunications infrastructure.